Ministry of Industry and Minerals
State Company for Sugar Industry
- Re Advertisement -
State company for sugar industry call the specialists and the experienced suppliers to participate in the below tender for providing the co. with the following material ; one (1) steam boiler , two(2) steam generator turbine ,the interested supplier have to visit the head quarter of the company in Misan governorate – almijar alkabeer strict to get the tender against non -refundable amount ( 200000 ) Dinar their offer should be submitted in the offer s box in the head quarter of the co. and the deadline for receiving the offers is 31/ 5 /2010 provided that
- For presentation of the offer ( bid ) it should be through only one specific company and the receiving the work according to ( turn key ) .
-The supplier should present the offer in three sealed envelope shows the name of the co. and the not .of tender and the material ,the first envelop is for technical offer and the second is for the commercial offer and the third envelop should contain the required below documents
- Company certificate
-Initial guaranties 1% of the amount of offer and it should be in the from of certificate check or guarantee letter from a fiducially Iraqi bank or a bond issued by Iraqi government on condition that when the tender awarded the performance bond should be completed to 5 %
- exemption
- receipt shows the purchasing of tender
- the company is not obliged to accept the lower price
-the cost of issuing and advertisement should be borne by supplier who get the tender
-Any offer which is not conformable with the general conditions would be neglected
- Also the co. call the whole participants to attends the opening of offers on 1/ 6/2010 as well as for any information ,the co. call the participants to attends the conference which is about to be held in its headquarter on 25/ 5/2010
From more information pls. visit our web site www. state sugar company .com
and ministry of industry web site www. industery .qov.iq
|
qty
|
Required material
|
Tender no.
|
Itm
|
|
1
|
Steam Boiler
|
1/t/sugar -2/2010
|
1-
|
|
2
|
Steam Generator Turbine
|
|
|
Boiler 100 ton / h
Description
1- one complete water tube natural circulation D type boiler with bidrums with following specification
1- 1 capacity 100 ton / h
1- design pressure 36bar working pressure 31 bar
1-3 super heated steam temp 390 + 10 Cْ
1-4 Boiler feedwater pump with motor number (2)
Type: Single suction horizontal multistage
Capacity: 130.000 M3/h
Total head : 45 kg/cm2
Handling liquid temp = 120Cْ
1-5 The boiler will work with black oil contemprarly, fuel oil for start up only, natural gas for future .
black oil specification .
gravity A..P.I 15.6c 8.0 min
flash point p.m .c 66 min
viscosity s.f.s.50c 300 max
pour point c 26.7 max
sulfur wt % 4.5 max
carbon residue 15 max
water & sediment 2.0 max
1-6 Deaeration system
With receiver tank capacity = 70 m3 .
2- The boiler system will include the following Itms .
2-1 Dual drive FD fan ( elect . motor and steam turbine ) with forced lubrication system .
2 -2 Ignitor and burner .
2-3 complete starter should be suitable for required fan circuit Breaker , Including vacuum meters ( volt meters & Ammeters )
Earth fault relay
Under voltage relay
Motor protection relay
Voltage transformers
Current Transformers
Power Fuse high voltage
Control Fuse
Auto restart relay in case under voltage less than 4sec .
2-4 complete computerized control system with ( PLC ) or ( DCS ) also the vendors must supply the software and programming unit if required and should be installed in dedicated room near the boiler .
2-5 The specification of feed water exist
PH=8.0 – 9.5 Hardness as caco3 = 0
Dissolved oxygen less than 0 – 03 ppm
Total solid less then 500 ppm
Silica less then 20 ppm
The vender should supply chemical injection skid including chemicals for on year opration as you're recommended .
2-6 Boiler to be supplied with all instrumentation Including sight glasses both sides ( level indicator ) ( double level transmitter for steam drum level with recorder ) O2 , CO2 analyzers .
2-7 smoke stack not less than 35M .
3- spare parts as following : ( boiler spare parts )
3-1 10 % spare part for pipes ( from S.D to W.D Furnace tube )
3-2 10 % spare part super heater coil .
3-3 10 % spare part Economizer coil .
3-4 spare parts for burner consist of ( tip of burner , control valve , vent valve , Igniter )
3-5 spare part for starter for 2 years power .
3-6 1 set of FD fan bearings
3-7 1 set of turbine bearings
3-8 1 set of motor bearings
3-9 complete coupling between motor & FD fan .
4- Training
The supplier will cover cost of training for 8 person in the manufacturer country or countries have the same boiler for 2 weeks .
5- 5-1 supplier should supply safety valves, manual valves with standards like ( ASME )
5-2 The supplier should provide manual for Insulation and Explain the method of working
5-3 supply Rolling machine ( hydraulic machine ) and Expander for tubes in steam drum and Water. drum and prefer hydraulic type with different type and size .
5-4 The control system should be DCS or PLC and supply all vendors requires .
6- supplier should complete all civil engineering works( foundation , anchor bolts , sheds, supports , Rooms , platfrom , stairway )
7- Insulation for whole system ( heat exchanger ) piping .
8- origin prefer, western Europe ,
Japan and U.S.A .
Steam Turbine Generator ( 2 )
Description
Capacity = 5.5 MW \ H
Inlet steam pressure = 20 – 25 bar max
Outlet steam pressure = 4.5 bar
Inlet steam temp = 360 + 10 Cْ
Complete instaltion in site , Exist foundation dimension = max , overall , dimensions of turbo
Longitudinal / axial 9100 mm
Vertical / IP 3300 mm
Transverse 4200 mm
( 2 )- Auxiliary lub oil system each turbine . output voltage 11 KV 50 HZ
Prefer RPM for electric dynamo = 1000 rpm or 1500
Synchronizing panel between tow generators and between tow generators and national net, Air circuit breaker 11 KV for each generator .
Inspection certification from specialized Authority whole job .
The supplier will cover cost of training for 8 person in the manufacturer country or countries have the same Steam turbine generator for 2 weeks .
Cooling water pumps suitable for the purpose with piping herewith photos for Exist steam turbine cooling water pond utility basin .
Announcement
The Mosul Sugar factory one of Ministry of Industry and Minerals formations announces a tender (1/SGR-1/2010) of designing, implementing and operating an industrial water treatment unit for Mosul Sugar and Yeast factories discharges, according to the permitted environmental limitations and standards of Rivers Maintenance and State Waters No. (25) for 1967 and its attached amendments .
Whoever specialized contracting companies, desire to participate in this tender shall present their bids to the commercial directorate / Mosul factories ending of official time in Tuesday (15/6/2010) and may obtain the tender conditions from the commercial directorate/ Mosul factories, for unrecoverable sum of (200000) ID, The bidder should submit (bid band) (1%) of total offer according to ratified check letter of credit or bank guarantee by depending Iraq bank .
For more information visit our website
www.Statesugarcompany.com
ministry of industry and minerals website
www.INDUSTRY.GOV.IQ
Director General
Ministry of Industry and Minerals
State Company of Sugar Industry
Mosul Sugar and Yeast factories
Tender No. 1/SGR-1/2010
The project includes establishing an integrated industrial and sanitary water treatment plant for Mosul Sugar, Yeast and Alcohol factories discharges applying zero ground method (TURN KEY JOB) .
The closing date
&n